Contracted scope of work
Documents produced under this engagement
| Deliverable | Type | Status | Owner | Updated |
|---|---|---|---|---|
|
grantham-meres-hdp-v1.0.pdf
|
Primary deliverable | Final | JH | 18 May 2026 |
|
psds-p4-application-bundle-v1.0.pdf
|
Primary deliverable | Final | JH | 18 May 2026 |
|
site-baseline-analysis-v1.2.xlsx
|
Working model | Final | SR | 02 May 2026 |
|
options-appraisal-matrix-v1.1.xlsx
|
Working model | Final | JH | 22 Apr 2026 |
|
energy-saving-calcs-unlocked-v1.0.xlsx
|
Grant evidence | Final | JH | 14 May 2026 |
|
grant-carbon-cost-calculator-v1.0.xlsx
|
Grant evidence | Final | JH | 14 May 2026 |
|
risk-register-v1.0.xlsx
|
Grant evidence | Final | JH + KM | 14 May 2026 |
|
feasibility-study-v1.0.pdf
|
Technical case | Final | KM | 30 Apr 2026 |
|
site-survey-report-v1.0.pdf
|
Technical evidence | Final | KM | 04 Apr 2026 |
|
boiler-nameplate-evidence-pack.zip
|
Grant evidence | Final | KM | 04 Apr 2026 |
|
dno-correspondence-v1.0.pdf
|
Technical evidence | Awaiting DNO surgery | KM | 16 May 2026 |
|
counter-fraud-declaration.pdf
|
Grant evidence | With client for signature | Client | — |
| … 11 more working documents (data extracts, schematics, supplementary tools) | ||||
Why this site qualifies for the Net Zero Pod®
| Criterion | Threshold | This site | Score | Notes |
|---|---|---|---|---|
| Wet leisure profile | Pool present · DHW dominant | 25m main pool + learner | Pool heating + DHW is ~73% of site demand | |
| End-of-life fossil plant | Boilers ≥10 yrs at decommission | 17–19 yrs (Hoval 2009 + 2011) | Strong PSDS eligibility case | |
| DNO capacity available | ≥525 kVA for pod + ancillaries | Indicative 525 kVA · awaiting confirmation | Fallback design at 425 kW pre-approved | |
| External space available | ≥40 m² external footprint clear of public area | Yes · S24-2106 planning approved Apr 2025 | Planning de-risked at engagement start | |
| Grant carbon cost competitiveness | <£510/tCO₂e LT cap | £323/tCO₂e LT projected | Top tier likely | |
| Operator alignment | Engaged operator + utility-paying landlord | 1Life op contract · SKDC pays utilities | No subsidy control complication |
Low-carbon heating options considered & discounted
| Option | Technical fit (30%) | Whole-life cost (25%) | Deliverability (20%) | Carbon (25%) | Total score | Outcome |
|---|---|---|---|---|---|---|
| District heat network connection | 2 / 10 | 5 / 10 | 3 / 10 | 9 / 10 | 4.6 / 10 | Reject No local network · >3km to nearest planned |
| Ground-source heat pump (GSHP) | 5 / 10 | 4 / 10 | 2 / 10 | 8 / 10 | 4.6 / 10 | Reject Clay subsoil · aquifer protection zone |
| Biomass | 4 / 10 | 6 / 10 | 5 / 10 | 5 / 10 | 5.0 / 10 | Reject Urban air-quality · supply chain risk |
| Electric boiler (no heat pump) | 7 / 10 | 2 / 10 | 9 / 10 | 6 / 10 | 5.6 / 10 | Reject Lifetime cost prohibitive · would breach £510 cap |
| Conventional site-built ASHP cascade (R32) | 8 / 10 | 6 / 10 | 5 / 10 | 7 / 10 | 6.5 / 10 | Reserve Viable fallback if Net Zero Pod factory slot unavailable |
| LE Net Zero Pod® (R744 CO₂) | 10 / 10 | 9 / 10 | 9 / 10 | 9 / 10 | 9.3 / 10 | Selected Highest total score · pre-commissioned · fastest deploy |
Working trail of consultant decisions
Confirmed scope: LCSF-funded HDP + PSDS application support. Out-of-scope: portal submission (client-led), delivery contract (separate procurement). SKDC's S151 (T. Halliwell) confirmed engagement letter terms.
Full plant inventory captured. Boiler nameplates photographed (Hoval UltraGas 575D × 2, commissioned 2009 + 2011). Thermal imaging of pool hall roof beams identified two thermal-bridge points. AHU VSDs found running fixed at 40 Hz with no modulation. Filed: site-survey-report-v1.0.pdf
Gas: 2,799,021 kWh CY2024 · Elec: 245,057 kWh CY2024. Data coverage 98.5%; 2 days missing (Aug 12–14, site closed). Tariffs locked Apr 2023–Mar 2026. Filed: site-baseline-analysis-v1.2.xlsx
All technical and commercial fit criteria met. Recommendation to proceed with Net Zero Pod as technical specification, subject to options-appraisal validation. Recorded conflict-of-interest disclosure (pod is LE product).
External technical peer review by Lockie Energy confirmed the scoring matrix, weightings, and discount rationale for non-pod options. No material adjustments. Filed: peer-review-lockie-v1.0.pdf
Following options appraisal (Pod score 9.3/10 vs site-built cascade 6.5/10), Net Zero Pod specified as the technical recommendation. Pod factory slot booked at LE Technology Centre, Kidderminster for Q4 2027 build.
Pool tank construction drawings unavailable. Mean depth assumed from typical 25m 6-lane competition + learner profile. Used for heat-loss and volume modelling. Flagged for surveyor verification on next site visit.
Grant carbon cost calculated at £323/tCO₂e LT — well within £510 cap. Application projected to fall in top tier (top 30%). HDP and PSDS application bundle prepared. Self-funded microfiltration excluded from grant submission to keep tier-1 placement.
Final HDP and PSDS application bundle released to T. Halliwell (SKDC Property) for Cabinet papers. Counter-fraud declaration sent for S151 signature. Engagement entering final close-out.
Calculation methodology & key assumptions used
Heat-loss calculations
Steady-state heat-loss method per CIBSE Guide A. U-values derived from on-site fabric survey + 1989-era construction archetype where not directly verifiable.
Carbon factors
DESNZ Greenhouse Gas Reporting Conversion Factors 2024: Gas 0.18290 kgCO₂/kWh · Grid electricity 0.20705 kgCO₂/kWh.
Heat-pump performance
sCOP target 4.64 based on LE Net Zero Pod® factory-rated performance at this site's duty profile (UK climate · pool DHW + space heating cascade).
Pool evaporation rate
Calculated using Smith-Lof-Tichy method with on-site measured air temp + RH. Pool surface area from S24-2106 site plans; mean depth assumed at 1.8m (unverified).
Grant carbon cost
Per Phase 4 PSDS Guidance §2.2.1: Grant value requested ÷ direct lifetime tCO₂e saved by grant-funded measures.
Future grid trajectory
Linear decline from 0.207 (2024) to 0.030 (2050) kgCO₂/kWh per DESNZ central scenario. Used for 20-year payback projections.
Engagement commercials & conflict-of-interest disclosure
Prepared by
287–291 Banbury Road · Oxford · OX2 7JQ
Independent peer review
Manchester · CIBSE Low Carbon Consultant